Solar PV and battery storage are both on Thornton's permit list and both qualify for rapid review. The City's fee schedule treats solar differently from other electrical work.

Updated November 20, 2026. Sources: City of Thornton, Colorado DORA, utilities and published cost data.

At a glance

Permit
Required for solar PV and battery storage
Review
Eligible for rapid review
Valuation
$3.50 per watt
Residential fee cap
$500

Permit and review

The City lists solar PV systems and battery storage among outside projects that need a permit, and backup generators and energy storage systems among inside ones. Reinstalling existing solar PV does not need a permit. (Permit requirements) Solar PV systems and energy storage systems are both eligible for the City's rapid review. (Rapid review list)

What the City asks for

The City's solar submittal requirements ask for plans through the CityView portal, a separate review for each address, and a signed contract showing total labor and material cost that matches the value on the application. Residential plans need a layout of service equipment, disconnects, meters, inverters, batteries and arrays, and a one-line diagram with conductor, breaker, inverter and disconnect ratings. Any main panel upgrade must be split out into its own panel upgrade permit. The structural part of residential plans must be stamped by a Colorado professional engineer. (Solar submittal requirements)

Fees

Thornton's 2026 fee schedule values solar at $3.50 per watt and caps the solar permit fee at $500 for residential systems. (Fee schedule) A panel upgrade done with the solar job is permitted and priced separately (see panel upgrades).

Utility interconnection

Your utility, Xcel Energy or United Power depending on address, has its own interconnection process for solar and batteries. (City of Thornton) Ask the installer who files it and how long it is taking.

Questions Thornton homeowners ask

Does Thornton cap solar permit fees?

Yes. The City's 2026 fee schedule values solar at $3.50 per watt and caps the residential solar permit fee at $500.

Do I need a permit to reinstall existing solar panels in Thornton?

The City lists existing solar PV reinstallation among outside projects that do not need a permit. A new system or added battery does need one.